Monday, March 3, 2008


This morning John & Ron were snapping lines to locate all the interior walls and Bert got started laying out the framing for the end wall of the garage. Corey worked at putting the OSB sheathing on the basement. The Rep from BJ's Truss came out to take final measurements and found a couple of problem areas: There is a 12 foot alcove over the tub in the master bathroom that was overlooked and he has a problem with the area where the stairway goes up to a bonus room above the garage. One of the walls is engineered for load bearing with tie downs and he has to locate 2 drag trusses so they transfer load onto that wall but there are height differences that interfere. He was to call us if he needed any changes and we received no call, so hopefully he solved the problem. John & Bert were going to Eugene in the afternoon.