Friday & Saturday I worked on emptying out the garage & getting things ready for the cement pour I had scheduled for Monday. Bud Ransom & Pedro were here at 6:30 AM to begin setting up. The truck was due at 8:00 AM. The pour went well except for the middle where the inexperienced driver let to much cement down the chute. There was a big pile right in the center of our garage. Bud was not happy! He & Pedro had to rake most of the cement over to the far side to get things evened out. This was hard work & they aren't getting any younger. These guys are craftsmen & gave us a good looking floor with two expansion joints.


John, Ron & Bert walked up the hill at 7 AM & discussed the framing that remained. They headed out to Freres Lumber for supplies & were hard at work before 8 AM. I was busy taking pictures of the cement work and didn't take any shots of the framing work until today. John & Ron will be back on Saturday to finish up the arch above our entry and the arch over the other window.