Tuesday we passed inspection on the rain drain system and got an OK to cover but I was required to add a clean out and put tracer wire on all the long runs away from the footings & foundation. I completed that yesterday & called Logan to schedule a date for backfill. He was just getting ready to leave town for a few weeks of vacation and had no work in progress. He can always use a few more $$, so he is coming by first thing today & expects to have most of the work we need before leaving town. Jose put the final touches on the interior trim last week & Lynna is pleased with the way her paint color selection turned out. Sherry & Paul: see my comment added below the previous post. :)